BREEAM:

GEP Design Consultants provide BREEAM Assessment Services for Healthcare Facilities utilising BRE’s current assessment tools.

We can assess the energy and efficiency and sustainability for both new and existing Healthcare buildings using BREEAM procedures and work tools.

The three stages used to assess new developments are:

Pre-assessment

The first stage provides advice that allows for an early informal view of the sustainability of a development and provides advice on the elements that need to be incorporated into the detailed design and cost plan. 

Pre-assessment Advice

Provision of a facilitation meeting, during which base design parameters will be explored against the relevant BREEAM criteria. Review of current scheme information with regards to the BREEAM criteria. Provision of pre-assessment document indicating the baseline rating and suggesting what uplift in specifications would be required to reach the desired rating. Provision of a Target/Planning document indicating the target credit rating.Provide advice on BREEAM issues as required.

 

 

 

Interim Assessment

The interim assessment is usually carried out at RIBA stages C to D once the detailed drawings, calculations and specifications are available.

Certified Interim Assessment

Issue of an Information Required Schedule to design team. Review information submitted for formal assessment. Provision of interim reports indicating what has been achieved and listing further information required. (3 interim reports assumed). Formal Initial Assessment. Attending meeting to go through any outstanding information or issues raised during the formal assessment. Provision of Final Design Report. Issue to BRE for Interim Certification.

 

 

Final Certified Assessment

The final certified assessment is carried out just prior to hand over and is based on the as built drawings, calculations and a site inspection. 

Certified Final Assessment

Issue of Information Required Schedule to the design team. Review as built drawings and specification against Interim information. Onsite inspection to verify construction. Provision of interim reports indicating what has been achieved and listing further information required.

(2 interim reports assumed). Provision of Final Report. Issue to BRE for Final Certification.